Bolting the Center RPSL’s in place. Notice the fancy notches we had to put in for them.
Tue 30 Sep 2003

Bolting the Center RPSL’s in place. Notice the fancy notches we had to put in for them.
Tue 30 Sep 2003

Why hire a crane and operator when Ya can make yer own; The Tarheel Crane in operation setting the center Ridge Pole Support logs. Was all set to hire a crane or boom truck to get the center R.P.S.L.’s set into place and then my neighbor Tommy told me to let him figure it out… Tommy chained a log to his loader and we made our own crane!! ![]()
Tue 30 Sep 2003

Cutting in the windows and door openings with a little help from friend David Dellinger!
NOTE: We drove rebar 2′ On Center in every course and in every log… NOT a good idea if you already have your window and door placement already pre-planned!! We went through 3 chainsaw chains cutting out the windows and doors by nicking a piece of rebar in the way. All rebar does not drive straight… some may hit a knot or some other thing in your log and turn. Take the time and plan out your windows and doors and leave the rebar out there.
Tue 9 Sep 2003

9/9/03 9th course of logs all done and ready for the last layer of logs,..WAHOO!!!
:-)
Sun 7 Sep 2003

Setting and driving rebar in the 8th course of logs by sun-set. ![]()
Wed 3 Sep 2003

9/3/03 set, drilled and drove all the rebar in the 7th course and set the 8th course with some help from neighbors. ![]()